Skip to content
← Find this measure

2011 Regular Session · HB 2619

Introduced — HB 2619 (2011R1)

This is extracted document text. Strikeouts, bold additions, columns, and tables may not survive extraction. Check the original PDF when comparing amendments.

Other indexed documents for this measure (2)
Recorded legislative activity (4)
  1. First Reading Of House Bills
  2. First reading. Referred to the desks of the Co-Speakers.
  3. Referred to General Government and Consumer Protection.
  4. In committee upon adjournment.
Citation and provenance

Oregon Legislature. Introduced — HB 2619 (2011R1). 2011 Regular Session. https://olis.oregonlegislature.gov/liz/2011R1/Downloads/MeasureDocument/HB2619/Introduced Retrieved 2026-09-02.

Document ID: doc_c596d2a8147d9a8ac50d

Original SHA-256: 44acefa116df34976714905928f5494ffac4947e8f9bb389863d76901ef6e0d0

Extracted text SHA-256: 087ec34f9c2759d6424096a4abad719e9963fd485eaa28e90e4c6c0c3de64735

                                 76th OREGON LEGISLATIVE ASSEMBLY--2011 Regular Session



                                              House Bill 2619
     Sponsored by Representative SCHAUFLER (Presession filed.)


                                                             SUMMARY
     The following summary is not prepared by the sponsors of the measure and is not a part of the body thereof subject
     to consideration by the Legislative Assembly. It is an editor’s brief statement of the essential features of the
     measure as introduced.

         Permits contracting agency to consider bidder’s record of relations with subcontractors in
     evaluating bidder’s responsibility for purposes of awarding public contract.
         Permits contracting agency or Construction Contractors Board to disqualify person from con-
     sideration for award of contracting agency’s contracts if person violates provisions of law regulating
     conduct between contractor and subcontractor.
         Requires contractor to provide and use specific form and administrative procedures for pro-
     cessing payments due to subcontractors and prohibits contractor from delaying, withholding or de-
     nying payment on basis of change in form or administrative procedures.
         Declares emergency, effective on passage.

 1                                                   A BILL FOR AN ACT
 2   Relating to obligations between contractors on public contracts; creating new provisions; amending
 3        ORS 279C.375, 279C.440 and 279C.580; and declaring an emergency.
 4   Be It Enacted by the People of the State of Oregon:
 5        SECTION 1. ORS 279C.375 is amended to read:
 6        279C.375. (1) After a contracting agency has opened bids and determined that the contracting
 7   agency will award a public improvement contract, the contracting agency shall award the contract
 8   to the lowest responsible bidder.
 9        (2) At least seven days before awarding a public improvement contract, unless the contracting
10   agency determines that seven days is impractical under rules adopted under ORS 279A.065, the
11   contracting agency shall issue to each bidder or post, electronically or otherwise, a notice of the
12   contracting agency’s intent to award a contract. This subsection does not apply to a contract to
13   which competitive bidding does not apply under ORS 279C.335 (1)(c) or (d). The notice and the
14   manner in which the contracting agency posts or issues the notice [is posted or issued] must
15   conform to rules adopted under ORS 279A.065.
16        (3) In determining the lowest responsible bidder, a contracting agency shall do all of the fol-
17   lowing:
18        (a) Check the list created by the Construction Contractors Board under ORS 701.227 for bidders
19   who are not qualified to hold a public improvement contract.
20        (b) Determine whether the bidder is responsible. A responsible bidder must demonstrate to the
21   contracting agency that the bidder:
22        (A) Has available the appropriate financial, material, equipment, facility and personnel resources
23   and expertise, or has the ability to obtain the resources and expertise, necessary to meet all con-
24   tractual responsibilities.
25        (B) Holds current licenses that businesses or service professionals operating in this state must
26   hold in order to undertake or perform the work specified in the contract.
27        (C) Is covered by liability insurance and other insurance in amounts the contracting agency



     NOTE: Matter in boldfaced type in an amended section is new; matter [italic and bracketed] is existing law to be omitted.
     New sections are in boldfaced type.

     LC 2248
                                               HB 2619


 1   requires in the solicitation documents.
 2       (D) Qualifies as a carrier-insured employer or a self-insured employer under ORS 656.407 or has
 3   elected coverage under ORS 656.128.
 4       (E) Has made the disclosure required under ORS 279C.370.
 5       (F) Completed previous contracts of a similar nature with a satisfactory record of performance.
 6   For purposes of this subparagraph, a satisfactory record of performance means that to the extent
 7   that the costs associated with and time available to perform a previous contract remained within
 8   the bidder’s control, the bidder stayed within the time and budget allotted for the procurement and
 9   otherwise performed the contract in a satisfactory manner. The contracting agency shall document
10   the bidder’s record of performance if the contracting agency finds under this subparagraph that the
11   bidder is not responsible.
12       (G) Has a satisfactory record of integrity. The contracting agency in evaluating the bidder’s
13   record of integrity may consider, among other things, whether the bidder has previous criminal
14   convictions for offenses related to obtaining or attempting to obtain a contract or subcontract or in
15   connection with the bidder’s performance of a contract or subcontract and whether the bidder in
16   previous public contracts complied with the provisions of ORS 279C.580 and otherwise had a
17   satisfactory record of relations with the bidder’s previous subcontractors. The contracting
18   agency shall document the bidder’s record of integrity if the contracting agency finds under this
19   subparagraph that the bidder is not responsible.
20       (H) Is legally qualified to contract with the contracting agency.
21       (I) Supplied all necessary information in connection with the inquiry concerning responsibility.
22   If a bidder fails to promptly supply information concerning responsibility that the contracting
23   agency requests, the contracting agency shall determine the bidder’s responsibility based on avail-
24   able information, or may find that the bidder is not responsible.
25       (c) Document the contracting agency’s compliance with the requirements of paragraphs (a) and
26   (b) of this subsection in substantially the following form:
27   _______________________________________________________________________________________
28
29                                RESPONSIBILITY DETERMINATION FORM
30
31   Project Name:
32   Bid Number:
33   Business Entity Name:
34   CCB License Number:
35   Form Submitted By (Contracting Agency):
36   Form Submitted By (Contracting Agency Representative’s Name):
37        Title:
38        Date:
39        (The contracting agency must submit this form with attachments, if any, to the Construction
40   Contractors Board within 30 days after the date of contract award.)
41        The contracting agency has (check all of the following):
42       [ ] Checked the list created by the
43           Construction Contractors Board
44           under ORS 701.227 for bidders who
45           are not qualified to hold a public


                                                  [2]
                                            HB 2619


 1       improvement contract.
 2   [ ] Determined whether the bidder has
 3       met the standards of responsibility.
 4       In so doing, the contracting agency
 5       has found that the bidder
 6       demonstrated that the bidder:
 7       [ ] Has available the appropriate
 8           financial, material, equipment,
 9           facility and personnel resources
10           and expertise, or the ability to
11           obtain the resources and
12           expertise, necessary to meet
13           all contractual responsibilities.
14       [ ] Holds current licenses that
15           businesses or service professionals
16           operating in this state must hold
17           in order to undertake or perform
18           the work specified in the contract.
19       [ ] Is covered by liability insurance
20           and other insurance in amounts
21           required in the solicitation
22           documents.
23       [ ] Qualifies as a carrier-insured
24           employer or a self-insured
25           employer under ORS 656.407 or has
26           elected coverage under ORS 656.128.
27       [ ] Has disclosed the bidder’s first-
28           tier subcontractors in accordance
29           with ORS 279C.370.
30       [ ] Has a satisfactory record of
31           performance.
32       [ ] Has a satisfactory record of
33           integrity.
34       [ ] Is legally qualified to contract
35           with the contracting agency.
36       [ ] Has supplied all necessary
37           information in connection with
38           the inquiry concerning
39           responsibility.
40   [ ] Determined the bidder to be
41       (check one of the following):
42       [ ] Responsible under ORS 279C.375
43           (3)(a) and (b).
44       [ ] Not responsible under
45           ORS 279C.375 (3)(a) and (b).


                                                 [3]
                                                HB 2619


 1       (Attach documentation if the contracting agency finds the bidder not to be responsible.)
 2   _______________________________________________________________________________________
 3
 4       (d) Submit the form described in paragraph (c) of this subsection, with any attachments, to the
 5   Construction Contractors Board within 30 days after the date the contracting agency awards the
 6   contract.
 7       (4) The successful bidder shall:
 8       (a) Promptly execute a formal contract; and
 9       (b) Execute and deliver to the contracting agency a performance bond and a payment bond when
10   required under ORS 279C.380.
11       (5) [Based on competitive bids,] A contracting agency, on the basis of competitive bids, may
12   award a public improvement contract or may award multiple public improvement contracts when
13   specified in the invitation to bid.
14       (6) A contracting agency may not exclude a commercial contractor from competing for a public
15   contract on the basis that the license issued by the Construction Contractors Board is endorsed as
16   a level 1 or level 2 license. As used in this section, “commercial contractor” has the meaning given
17   that term in ORS 701.005.
18       SECTION 2. ORS 279C.440 is amended to read:
19       279C.440. (1)(a) A contracting agency may disqualify a person from consideration for award of
20   the contracting agency’s contracts for the reasons listed in subsection (2) of this section after pro-
21   viding the person with notice and a reasonable opportunity to be heard.
22       (b) In lieu of the disqualification process described in paragraph (a) of this subsection, a con-
23   tracting agency contracting for a public improvement may petition the Construction Contractors
24   Board to disqualify a person from consideration for award of the contracting agency’s public im-
25   provement contracts for the reasons listed in subsection (2) of this section. The Construction Con-
26   tractors Board shall provide the person with notice and a reasonable opportunity to be heard.
27       (c) A contracting agency or the Construction Contractors Board may not disqualify a person
28   under this section for a period of more than three years.
29       (2) A person may be disqualified from consideration for award of a contracting agency’s con-
30   tracts for any of the following reasons:
31       (a) The person [has been] was convicted of a criminal offense as an incident in obtaining or at-
32   tempting to obtain a public or private contract or subcontract, or in the performance of such con-
33   tract or subcontract.
34       (b) The person [has been] was convicted under state or federal statutes of embezzlement, theft,
35   forgery, bribery, falsification or destruction of records, receiving stolen property or any other of-
36   fense indicating a lack of business integrity or business honesty that currently, seriously and di-
37   rectly affects the person’s responsibility as a contractor.
38       (c) The person [has been] was convicted under state or federal antitrust statutes.
39       (d) The person [has committed a violation of] violated a contract provision that [is regarded by]
40   the contracting agency or the Construction Contractors Board [to be] regards as so serious as to
41   justify disqualification. A violation may include but is not limited to a failure to perform the terms
42   of a contract, [or] an unsatisfactory performance in accordance with the terms of the contract or
43   knowingly and repeatedly failing to pay the person’s subcontractors in accordance with the
44   terms of a subcontract. However, a failure to perform or an unsatisfactory performance caused
45   by acts beyond the control of the contractor may not be considered to be a basis for disqualification.


                                                  [4]
                                               HB 2619


 1        (e) The person does not carry workers’ compensation or unemployment insurance as required
 2   by statute.
 3        (f) The person violated the provisions of ORS 279C.580.
 4        (3) A contracting agency or the Construction Contractors Board shall issue a written decision
 5   to disqualify a person under this section. The decision shall:
 6        (a) State the reasons for the action taken; and
 7        (b) Inform the disqualified person of the appeal right of the person under:
 8        (A) ORS 279C.445 and 279C.450 if the decision to disqualify was issued by a contracting agency;
 9   or
10        (B) ORS chapter 183 if the decision to disqualify was issued by the Construction Contractors
11   Board.
12        (4) A copy of the decision issued under subsection (3) of this section must be mailed or otherwise
13   furnished immediately to the disqualified person.
14        SECTION 3. ORS 279C.580 is amended to read:
15        279C.580. (1) A contractor may not request payment from [the] a contracting agency of any
16   amount withheld or retained in accordance with subsection (5) of this section until [such time as]
17   the contractor has determined and certified to the contracting agency that the subcontractor has
18   determined and certified to the contracting agency that the subcontractor is entitled to the payment
19   of [such] the amount.
20        (2) A dispute between a contractor and a first-tier subcontractor relating to [the amount or
21   entitlement of a first-tier subcontractor to a payment or a late payment interest penalty under] a clause
22   included in the subcontract under subsection (3) or (4) of this section does not constitute a dispute
23   to which the contracting agency is a party. The contracting agency may not be included as a party
24   in [any] an administrative or judicial proceeding involving [such a] the dispute.
25        (3) [Each public improvement contract awarded by] A contracting agency shall include [a clause]
26   in each public improvement contract the contracting agency awards a clause that requires the
27   contractor to include in each subcontract for property or services that the contractor enters into
28   with [entered into by the contractor and] a first-tier subcontractor, including a material supplier, for
29   the purpose of performing a construction contract:
30        (a) A payment clause that obligates the contractor to pay the first-tier subcontractor for satis-
31   factory performance under [its] the subcontract within 10 days out of [such] amounts [as are paid
32   to] that the contracting agency pays to the contractor [by the contracting agency] under the con-
33   tract; [and]
34        (b) A clause under which the contractor:
35        (A) Must provide the first-tier subcontractor with a standard form the first-tier subcon-
36   tractor may use as an invoice or other method with which to claim a payment due from the
37   contractor;
38        (B) Must use the same form and regular administrative procedures for processing pay-
39   ments during the entire term of the subcontract; and
40        (C) May not use changes in the form or the contractor’s administrative procedures as a
41   basis for delaying, withholding or denying a payment that is due; and
42        [(b)] (c) An interest penalty clause that obligates the contractor, if the contractor does not
43   pay the first-tier subcontractor [payment is not made] within 30 days after [receipt of] the con-
44   tractor receives payment from the contracting agency, to pay to the first-tier subcontractor an
45   interest penalty on amounts due [in the case of] for each payment [not made] the contractor does


                                                  [5]
                                               HB 2619


 1   not make in accordance with the payment clause included in the subcontract under paragraph (a)
 2   of this subsection. A contractor or first-tier subcontractor [may not be] is not obligated to pay an
 3   interest penalty if the only reason that the contractor or first-tier subcontractor did not make pay-
 4   ment when payment was due is that the contractor or first-tier subcontractor did not receive pay-
 5   ment from the contracting agency or contractor when payment was due. The interest penalty [shall
 6   be] is:
 7       (A) For the period beginning on the day after the required payment date and ending on the date
 8   on which payment of the amount due is made; and
 9       (B) Computed at the rate specified in ORS 279C.515 (2).
10       (4) [The contract awarded by] The contracting agency shall require in a contract with a con-
11   tractor that the contractor [to include in each of the contractor’s subcontracts, for the purpose of
12   performance of such contract condition, a provision requiring] in turn require in each subcontract
13   with a first-tier subcontractor that:
14       (a) The first-tier subcontractor [to] include [a payment clause and an interest penalty clause con-
15   forming] clauses that conform to the standards of subsection (3) of this section in each of the
16   first-tier subcontractor’s subcontracts; and
17       (b) [to require each of] That the first-tier subcontractor’s subcontractors [to] include [such]
18   clauses that conform to the standards of subsection (3) of this section in [their] subcontracts
19   with [each] lower-tier [subcontractor or supplier] subcontractors or suppliers.
20       (5)(a) The clauses required by subsections (3) and (4) of this section [are not intended to] do not
21   impair the right of a contractor or a subcontractor at any tier to negotiate, and to include in the
22   subcontract, provisions that permit the contractor or the subcontractor to:
23       (A) [Permit the contractor or a subcontractor to] Retain, in the event of a good faith dispute, an
24   amount not to exceed 150 percent of the amount in dispute from the amount due a subcontractor
25   under the subcontract without incurring [any] an obligation to pay a late payment interest penalty,
26   in accordance with terms and conditions in the subcontract to which the parties agreed, [to by
27   the parties to the subcontract, giving such recognition as the parties consider appropriate to the ability
28   of a subcontractor] recognizing as the parties consider appropriate the subcontractor’s ability
29   to furnish a performance bond and a payment bond;
30       (B) [Permit the contractor or subcontractor to make a determination] Determine that part or all
31   of the subcontractor’s [request for] payment may be withheld in accordance with the subcontract
32   [agreement]; and
33       (C) [Permit such withholdings] Withhold the amount described in this paragraph without in-
34   curring [any] an obligation to pay a late payment interest penalty if:
35       (i) A notice conforming to the standards of subsection (8) of this section has been previously
36   furnished to the subcontractor; and
37       (ii) A copy of any notice [issued by] that a contractor issues under sub-subparagraph (i) of this
38   subparagraph has been furnished to the contracting agency.
39       (b) As used in this subsection, “good faith dispute” means a documented dispute concerning:
40       (A) Unsatisfactory job progress.
41       (B) Defective work not remedied.
42       (C) Third-party claims filed or reasonable evidence that claims will be filed.
43       (D) Failure to make timely payments for labor, equipment and materials.
44       (E) Damage to the [prime] contractor or a subcontractor.
45       (F) Reasonable evidence that the subcontract cannot be completed for the unpaid balance of the


                                                    [6]
                                              HB 2619


 1   subcontract [sum] price.
 2       (6) If, after [making application] applying to a contracting agency for payment under a contract
 3   but before [making a payment to] paying a subcontractor for the subcontractor’s performance cov-
 4   ered by [such] the application, a contractor discovers that all or a portion of the payment otherwise
 5   due the subcontractor is subject to withholding from the subcontractor in accordance with the
 6   subcontract [agreement], the contractor shall:
 7       (a) [Furnish to] Give the subcontractor a notice [conforming] that conforms to the standards
 8   of subsection (8) of this section as soon as practicable upon ascertaining the cause giving rise to a
 9   withholding, but [prior to] before the due date for subcontractor payment;
10       (b) [Furnish to] Give the contracting agency, as soon as practicable, a copy of the notice [fur-
11   nished] the contractor gave to the subcontractor under paragraph (a) of this subsection;
12       (c) Reduce the subcontractor’s progress payment by an amount not to exceed the amount spec-
13   ified in the notice of withholding [furnished] given under paragraph (a) of this subsection;
14       (d) Pay the subcontractor as soon as practicable after the correction of the identified subcon-
15   tract performance deficiency;
16       (e) Make [such] the payment described in paragraph (d) of this subsection within:
17       (A) Seven days after correction of the identified subcontract performance deficiency unless the
18   contractor must recover the funds [therefor must be recovered] necessary to pay the subcon-
19   tractor from the contracting agency because of a reduction under paragraph (f)(A) of this sub-
20   section; or
21       (B) Seven days after the contractor recovers [such] the funds from the contracting agency;
22       (f) Notify the contracting agency upon:
23       (A) Reduction of the amount of any subsequent certified application for payment; or
24       (B) Payment to the subcontractor of any withheld amounts of a progress payment, specifying:
25       (i) The amounts of the progress payments withheld under paragraph (a) of this subsection; and
26       (ii) The dates that such withholding began and ended; and
27       (g) Be obligated to pay to the contracting agency an amount equal to interest on the withheld
28   payments computed in the manner provided in ORS 279C.570 from the 11th day after receipt of the
29   withheld amounts from the contracting agency until:
30       (A) The day the identified subcontractor performance deficiency is corrected; or
31       (B) The date that any subsequent payment is reduced under paragraph (f)(A) of this subsection.
32       (7)(a) If a contractor, after [making payment to] paying a first-tier subcontractor, receives from
33   a supplier or subcontractor of the first-tier subcontractor a written notice asserting a deficiency in
34   [such] the first-tier subcontractor’s performance under the contract for which the contractor may
35   be ultimately liable and the contractor determines that all or a portion of future payments otherwise
36   due [such] the first-tier subcontractor is subject to withholding in accordance with the subcontract
37   [agreement], the contractor may, without incurring an obligation to pay a late payment interest
38   penalty under subsection (6)(e) of this section:
39       (A) [Furnish to] Give the first-tier subcontractor a notice [conforming] that conforms to the
40   standards of subsection (8) of this section as soon as practicable upon making [such] the determi-
41   nation; and
42       (B) Withhold from the first-tier subcontractor’s next available progress payment or payments an
43   amount not to exceed the amount specified in the notice of withholding [furnished] given under
44   subparagraph (A) of this paragraph.
45       (b) As soon as practicable, but not later than 10 days after [receipt of] receiving satisfactory


                                                   [7]
                                              HB 2619


 1   written notification that the identified subcontract performance deficiency has been corrected, the
 2   contractor shall pay the amount withheld under paragraph (a)(B) of this subsection to [such] the
 3   first-tier subcontractor, or shall incur an obligation to pay a late payment interest penalty to
 4   [such] the first-tier subcontractor computed at the rate specified in ORS 279C.570.
 5       (8) The contractor shall give a written notice of any withholding [shall be issued] to a sub-
 6   contractor, with a copy to the contracting agency [of any such notice issued by a contractor], speci-
 7   fying:
 8       (a) The amount to be withheld;
 9       (b) The specified causes for the withholding under the terms of the subcontract; and
10       (c) The remedial actions [to be taken by] the subcontractor must take in order to receive pay-
11   ment of the amounts withheld.
12       (9) Except as provided in subsection (2) of this section, this section does not limit or impair any
13   contractual, administrative or judicial remedies otherwise available to a contractor or a subcon-
14   tractor in the event of a dispute involving late payment or nonpayment by a contractor or deficient
15   performance or nonperformance by a subcontractor.
16       (10) A contractor’s obligation to pay a late payment interest penalty to a subcontractor under
17   the clause [included in a subcontract under] described in subsection (3) or (4) of this section is not
18   [intended to be] an obligation of the contracting agency. A contract modification may not be made
19   for the purpose of providing reimbursement of [such] a late payment interest penalty.       A cost re-
20   imbursement claim may not include [any] an amount for reimbursement of [such] a late payment
21   interest penalty.
22       SECTION 4. The amendments to ORS 279C.375, 279C.440 and 279C.580 by sections 1 to 3
23   of this 2011 Act apply to contracts that a contracting agency first advertises or otherwise
24   solicits on or after the operative date specified in section 5 of this 2011 Act or, if the con-
25   tracting agency does not advertise or solicit the contract, to contracts that the contracting
26   agency first enters into on or after the operative date specified in section 5 of this 2011 Act.
27       SECTION 5. (1) The amendments to ORS 279C.375, 279C.440 and 279C.580 by sections 1 to
28   3 of this 2011 Act become operative on January 1, 2012.
29       (2) The Director of the Oregon Department of Administrative Services, the Attorney
30   General or a contracting agency that adopts rules under ORS 279A.065 may take any action
31   before the operative date specified in subsection (1) of this section that is necessary to enable
32   the director, the Attorney General or the contracting agency to exercise, on and after the
33   operative date specified in subsection (1) of this section, all of the duties, functions and
34   powers conferred on the director, the Attorney General or the contracting agency by the
35   amendments to ORS 279C.375, 279C.440 and 279C.580 by sections 1 to 3 of this 2011 Act.
36       SECTION 6. This 2011 Act being necessary for the immediate preservation of the public
37   peace, health and safety, an emergency is declared to exist, and this 2011 Act takes effect
38   on its passage.
39




                                                 [8]