2007 REGULAR SESSION · SB 838
Staff Measure Summary — SB 838 (2007R1)
This is extracted document text. Strikeouts, bold additions, columns, and tables may not survive extraction. Check the original PDF when comparing amendments.
Other indexed documents for this measure (12)
- Staff Measure Summary — SB 838 (2007R1)
- Staff Measure Summary — SB 838 (2007R1)
- Staff Measure Summary — SB 838 (2007R1) · open
- A-Engrossed — SB 838 (2007R1)
- B-Engrossed — SB 838 (2007R1)
- C-Engrossed — SB 838 (2007R1)
- Enrolled — SB 838 (2007R1)
- House Amendments to A-Engrossed — SB 838 (2007R1)
- House Amendments to B-Engrossed — SB 838 (2007R1)
- Introduced — SB 838 (2007R1)
- Senate Amendments — SB 838 (2007R1)
- OLIS measure summary
Recorded legislative activity (57)
- Introduction and First Reading Of Senate Measures
- Introduction and first reading. Referred to President's desk.
- Referred to Environment and Natural Resources.
- Heard
- Public Hearing held.
- Heard
- Public Hearing and Work Session held.
- Heard
- Public Hearing held.
- Heard and Reported Out with Amendments
- Work Session held.
- Recommendation: Do pass with amendments. (Printed A-Eng.)
- Second Reading Of Senate Measures
- Second reading.
- Third Reading Of Senate Measures
- Made a Special Order of Business by voice vote.
- Third reading. Carried by Atkinson, Avakian. Passed.
- Nelson declared potential conflict of interest.
- Vote explanation(s) filed by Verger.
- First Reading Of Senate Bills
- First reading. Referred to Speaker's desk.
- Referred to Energy and the Environment.
- Heard
- Public Hearing held.
- Heard
- Public Hearing held.
- Heard
- Public Hearing held.
- Not Heard
- Not Heard
- Not Heard
- Heard and Reported Out
- Work Session held.
- Not Heard
- Recommendation: Do pass with amendments and be printed B-Engrossed.
- Amendments distributed.
- Not Heard
- Second Reading Of Senate Bills
- Second reading.
- Third Reading Of Senate Bills
- Third reading.
- Motion to rerefer to Energy and the Environment carried. Rereferred.
- Heard and Reported Out
- Work Session held.
- Recommendation: Do pass with amendments and be printed C-Engrossed.
- Rules suspended. Made a Special Order of Business on May 23, 2007 Calendar.
- Special Orders Of Business
- Read. Carried by Dingfelder. Passed.
- Potential conflict(s) of interest declared by Jenson, Smith, G.
- Vote explanation(s) filed by Thatcher.
- Possible Consideration of House Amendments
- Senate concurred in House amendments and repassed bill.
- President signed.
- Speaker signed.
- Governor signed.
- Chapter 301, 2007 Laws.
- Effective date, June 6, 2007.
Citation and provenance
Oregon Legislature. Staff Measure Summary — SB 838 (2007R1). 2007 REGULAR SESSION. https://olis.oregonlegislature.gov/liz/2007R1/Downloads/MeasureAnalysisDocument/5449 Retrieved 2026-09-02.
Document ID: doc_f10dda352d4c8ccaebd7
Original SHA-256: ac8d69bf46f579a24f2806fd477ea9fa3f825282514d51ead0aa8768a4f56176
Extracted text SHA-256: 0b3987937d3c5514870a142606a68a59fc7e34aaac0e26f1404d00e40c58967f
74th OREGON LEGISLATIVE ASSEMBLY - 2007 Regular Session MEASURE: SB 838 B
STAFF MEASURE SUMMARY CARRIER: Rep. Dingfelder
House Committee on Energy and the Environment Rep. Cannon
REVENUE: Revenue statement issued
FISCAL: Fiscal statement issued
Action: Do Pass as Amended and Be Printed Engrossed
Vote: 4-3-0
Yeas: Beyer, Cannon, Macpherson, Dingfelder
Nays: Burley, Jenson, Smith G.
Exc.: -
Prepared By: Cat McGinnis, Administrator
Meeting Dates: 4/16, 4/18, 4/30
WHAT THE MEASURE DOES: Requires the Department of Energy to create a renewable portfolio standard under
which electric utilities must derive 25 percent of annual retail electricity sales from renewable energy resources by the
year 2025. Authorizes the Public Utility Commission (PUC) and consumer-owned utility governing boards to
establish procedures for implementation and monitoring of the renewable energy standard. Modifies and extends the
public purpose charge collected from retail customers until January 1, 2026. Declares an emergency, effective upon
passage.
ISSUES DISCUSSED:
• Provisions of the measure and proposed amendments
EFFECT OF COMMITTEE AMENDMENT:
• Amends definition of biogas to make clear that landfill gas is included
• Exempts certain hydroelectric facilities from geographic requirements
• Prohibits any public purpose charge other than the three percent provided for in statute
• Removes exemption applying only to firm commitments for electricity available to meet portions of utility’s
load requirement
• Allows a people’s utility district to become a member of an electric cooperative or of a limited liability company
for the purpose of operating or owning property for electricity generation or transmission
• Direct PUC to establish automatic adjustment clause allowing any individual to request full evidentiary hearing
prior to commission adopting proposed rate change
BACKGROUND: The renewable portfolio standard (RPS) sets a requirement that retail electricity providers supply a
minimum percent of their retail electricity load with eligible renewable energy sources by a certain date. The desired
objectives of RPS include: reducing greenhouse gas emissions, diversifying fuel sources, developing new
technologies, and improving rural economies. Most of the twenty-four states that have adopted an RPS have done so
in the last five years. The concept for an Oregon RPS came as a central recommendation in the 2005 report of the
Global Warming Advisory Group and was subsequently refined by a 32-member Renewable Energy Workgroup
appointed by Governor Kulongoski. Senate Bill 838-B, the Oregon Renewable Energy Act, establishes a renewable
energy standard of 25 percent of retail sales from renewable energy resources by 2025 as a means to accelerate the
transition to renewable energy sources and decrease Oregon’s reliance on fossil fuel for electric utilities. The measure
defines qualifying renewable electric energy facilities as those in existence or having expanded or improved efficiency
after January 1, 1995. Eligible renewable energy resources are defined in the measure to include wind, solar, wave,
geothermal, certain allowable biomass, and new hydro power sources.
5/10/2007 10:31:00 AM
This summary has not been adopted or officially endorsed by action of the committee.
Committee Services Form – 2007 Regular Session